Downtown Pavement Project
The City of Oskaloosa is planning street improvement projects in and around the downtown area beginning July 18, 2022, with completion on or before September 15, 2022.
Downtown Pavement Project Letter
Current Construction Schedule Update
Week of Aug 1st
- Continue removal and replacement of curb and gutter and sidewalk along 3rd Street from High Avenue to 1st Avenue (both sides), expect temporary lane closure (east side) and no angled parking (west side) lasting 7-10 days.
*Should be completed by Aug 5th
- Start removal and replacement of curb and gutter and sidewalk along 2nd Avenue from South 1st Street to South 2nd Street (both sides), expect temporary lane closure (both sides) and no angled parking (both sides) lasting 7-10 days.
Construction Schedule (subject to change):
Week of Aug 8th
- Concrete contractor will continue the removal and replacement of curb and gutter along 2nd Avenue from 1st Street to 2nd Street, expect temporary lane closures lasting 7-10 days.